The calculated duration of the project network plan is equal to ( )
A、Thelatestcompletiontimefortheworkrepresentedbytheendnodeinasingle-codenetworkplan;
B、Theearliestcompletiontimefortheworkrepresentedbytheendnodeinasinglecodenetworkplan;
C、Theearliesttimetocompletethelastcriticaltaskinthenetworkplan;
D、Themaximumvalueoftheearliestcompletiontimetoendworkinadual-codenetworkplan